Wins Parking

Transformer Service Upgrade for DC Fast EV Charging

The hidden line item in every DCFC project. kVA sizing math, demand-charge economics, utility cost-sharing programs, and 12 to 26 week lead times that determine whether your project hits its Section 30C deadline.

When DCFC Forces a Transformer Upgrade

Every existing commercial parking property has a utility pad-mount transformer, usually rated 500 to 1000 kVA for the building load plus a buffer. A single 350 kW DC fast charger draws 420 to 460 kVA at peak, so any property adding more than 600 kW of new DCFC capacity should expect a utility-driven transformer upgrade. Above 1.2 MW, a new pad-mount and primary feeder are unavoidable.

Make-ready vs turnkey deliveryMixed-power site design

Demand Charges and the Case for Battery Storage

Demand charges of $14 to $22 per kW per month are the largest operating cost at most DCFC sites — a 600 kW peak can add $8,400 to $13,200 per month uncontrolled. Sizing the transformer above peak load lets battery storage clip the peak the utility sees, cutting demand charges by 40 to 70 percent.

Solar canopy + battery storageNEVI & 30C capital stack

Lead Times and Cost-Sharing

An upgrade runs 12 to 26 weeks from formal service request to energized service, and 30 to 32 weeks in backlogged California and Texas metros. The 30C credit excludes transformers, but state make-ready programs in Colorado, California, and New York often cover 50 to 100 percent. We file the service request the day a project signs an LOI to start the clock early.

EV charging & parking management hubStart your transformer scope
Get a Free Quote