EV Charger and Robotaxi Charging Installation in Salt Lake City, UT
Wins Parking plans, permits, builds and runs EV charging for Salt Lake City properties, from downtown and University garages to distribution yards west of the airport. Rocky Mountain Power pays Utah business charger rebates, and the city's code sets both a minimum and a maximum for each use. The Department of Energy lists 522 public Level 2 and 109 DC fast ports in Salt Lake City.
- public Level 2 ports (AFDC)
- 522public Level 2 ports (AFDC)
- public DC fast ports (AFDC)
- 109public DC fast ports (AFDC)
- last day to place in service for the 30C credit
- June 30, 2026last day to place in service for the 30C credit
- to SLC, the service airport
- 3 mito SLC, the service airport
Get a free EV charger quote in Salt Lake City
Salt Lake City by the numbers
Minimums and maximums
Table 21A.44.040-A sets a minimum and a maximum for each use (updated Oct. 2022)
Salt Lake City Council, Off-street parking updatesChecked Oct 14, 2026
522 L2 · 109 DC fast
Public charging ports in Salt Lake City, pulled Oct 14, 2026
DOE Alternative Fuels Data Center, alt-fuel-stations APIChecked Oct 14, 2026
May–Sep work season
Months with average lows at or above 50°F; 51.9 in. of snow and 62.2 days at 90°F+ a year
NOAA NCEI, U.S. Climate Normals 1991-2020Checked Oct 14, 2026
100.9 cost index
Salt Lake City-Murray, UT Regional Price Parity, 2024 (U.S. = 100)
BEA Regional Price Parities, 2024Checked Oct 14, 2026
SLC · 3 miles
Salt Lake City International Airport, the service airport for Salt Lake City
Great-circle distance from the Census Gazetteer point to the airportChecked Oct 14, 2026
The chargers
Which EV chargers suit Salt Lake City parking lots?
Salt Lake City lists 522 public Level 2 and 109 DC fast ports in AFDC data pulled Oct 14, 2026; Level 2 fits downtown offices, the university and hospitals, and fast charging fits fleets near the airport and I-15.
Downtown offices, apartments near TRAX stations and the hospital and university campuses suit Level 2. Fast charging fits the logistics parks west of the airport and travelers on I-15 and I-80.
Our Salt Lake City EV charging station installation guide covers the service; this page adds Rocky Mountain Power's rebates and the city data.
The depot
What does a Salt Lake City robotaxi charging depot need?
No operator has announced Salt Lake City as of Oct 14, 2026; the nearest city on Waymo's list is Las Vegas, about 362 miles southwest.
When a fleet arrives, its depot will need fast chargers, staging, cleaning bays, a rider curb and gated entry, plus plowable layouts for 51.9 inches of snow a year at the airport.
Owners redeveloping near the airport or the inland port area can reserve transformer pads and conduit now. Background: autonomous vehicle parking, future-proof parking design and the EV and AV deployment guide. See also robotaxi depot design in Salt Lake City.
Industrial land near the airport and along the I-215 belt gives a future depot room to stage cars and store plowed snow, which matters as much as charger count here.
The network
How many public EV chargers does Salt Lake City have?
Salt Lake City has 204 public stations with 522 Level 2 and 109 DC fast ports, per AFDC data pulled Oct 14, 2026.
For a city of about 200,000 that is a dense network, with many ports at downtown workplaces, campuses and public garages.
Month-by-month figures sit in our EV charging ports by metro research.
The 204 stations average 3.1 ports, and about 17% of ports are fast. A row of twelve at one lot would rank among the larger public sites in the city.
The power
Which utility serves Salt Lake City chargers, and what does it offer?
Rocky Mountain Power pays Utah business charger rebates for workplace, community and multifamily sites.
Amounts vary by site type, so we confirm eligibility before design and apply before equipment is ordered. The utility also reviews capacity first.
A year of bills and the panel schedule, gathered at the first visit, show how much spare capacity the site has.
The code
Which permits and codes apply to EV chargers in Salt Lake City?
Salt Lake City Building Services cites 30 days for commercial review. Wiring follows NEC Article 625, and accessible stalls follow U.S. Access Board guidance.
Table 21A.44.040-A sets a minimum and a maximum for each use, updated in October 2022. Converting stalls has to keep the count between both.
Thirty days is the published review; Rocky Mountain Power's service work runs on its own clock, so we file both together.
The incentives
What EV charging incentives are open to Salt Lake City sites?
Rocky Mountain Power's rebates lead; Utah programs are listed on the AFDC state page.
Owners here can no longer plan on 30C; the IRS Instructions for Form 8911 end it for chargers placed in service after June 30, 2026.
Workplace and multifamily sites get the most from these rebates.
Rocky Mountain Power's amounts differ for workplace, community and multifamily sites, so we confirm the site type with the utility before design.
The budget
What does EV charger installation cost in Salt Lake City, and how long does it take?
Twelve Salt Lake City Level 2 ports run about $48,400 to $109,000 installed and four DC fast ports about $202,000 to $605,000, before rebates, by our estimate.
The city's BEA index of 100.9 is close to the national average. We scale national per-port costs and AFDC's installation guidance to it; frozen ground moves trenching to warmer months.
Expect roughly 8–16 weeks for a Level 2 job on spare capacity and 26–52 for a fast-charging job with new service, after permits, by our estimate.
Per port, Salt Lake City comes to about $4,033 to $9,083 for Level 2 and $50,500 to $151,250 for fast charging before Rocky Mountain Power's incentives, by our estimate. Frozen ground can delay trenching to spring.
What would chargers cost in Salt Lake City?
Wins Parking estimateCharger type
Installed cost
$24,200–$54,500
Signed scope to energized
8–16 weeks
A Wins Parking estimate, not a quote: Level 2 at $4,000–$9,000 installed per port (U.S. average), scaled by Salt Lake City's BEA cost index of 100.9. Trenching distance, panel and transformer upgrades and utility lead time move it most. The federal 30C credit cannot be claimed for chargers placed in service after June 30, 2026.
The day to day
How are Salt Lake City chargers run day to day?
We operate Salt Lake City sites remotely and on foot: dynamic session pricing, idle fees once the grace period ends, 24-hour fault alerts, stall enforcement and a monthly statement for the owner.
Plow routes are planned around the chargers, and units are checked before winter.
The Salt Lake City parking management page covers gates and enforcement; EV charging parking management covers the charging side.
Salt Lake City International's normals show 51.9 inches of snow a year and a coldest-month low near 24°F, with 5 months averaging lows at or above 50°F. Winter inversions trap cold air in the valley for days, so we choose cold-rated cables, mount units above plow height and check every port before the first storm.
The neighbors
How does Salt Lake City compare with nearby metros for EV charging?
Salt Lake City's 522 Level 2 ports are nearly four times Boise's 136, about 294 miles northwest, per AFDC data pulled Oct 14, 2026.
Rocky Mountain Power also serves parts of Idaho, but Boise is on Idaho Power, which lists no business rebate.
Denver, about 378 miles east, has 1,411 public Level 2 ports and Waymo service.
| City | Electric utility | Permit office | Review time | Public ports (L2 · DC fast) |
|---|---|---|---|---|
| Salt Lake City, UT (this page) | Rocky Mountain Power | Salt Lake City Building Services | 30 days | 522 · 109 |
| Boise, ID | Idaho Power | Boise Planning and Development Services | 30 business days | 136 · 31 |
| Las Vegas, NV | NV Energy | City of Las Vegas Building and Safety | 3 weeks | 1005 · 558 |
| Denver, CO | Xcel Energy | Denver Community Planning and Development | 20 business days | 1411 · 210 |
| Phoenix, AZ | APS | Phoenix Planning and Development | 20 days | 759 · 165 |
| Rapid City, SD | Black Hills Energy | Rapid City Building Services | Not published (Wins estimate: 3–6 weeks) | 24 · 11 |
Review times are published targets unless marked as a Wins estimate. Ports: AFDC, public and open, pulled Oct 14, 2026.
FAQ
Salt Lake City EV and robotaxi charging: frequently asked questions
Yes, for workplace, community and multifamily sites. Amounts vary by site type.
No operator has announced service. The nearest Waymo city is Las Vegas, about 362 miles away. Wins has no robotaxi client in Utah.
522 Level 2 and 109 DC fast ports at 204 public stations, per the Department of Energy on Oct 14, 2026.
Salt Lake City Building Services cites 30 days.
The code sets a minimum and a maximum for each use, so conversions must stay between them.
The airport averages 51.9 inches a year, so we plan plow routes and place chargers on raised pads.
Spring through fall is easiest. 5 months average lows at or above 50°F, and frozen ground slows winter trenching.
About $48,400 to $109,000 for twelve ports installed before rebates, by our estimate.
Sources
- DOE Alternative Fuels Data Center, Electric Vehicle Charging Stations, checked Oct 14, 2026
- DOE Alternative Fuels Data Center, Procurement and Installation, checked Oct 14, 2026
- DOE Alternative Fuels Data Center, alt-fuel-stations API, checked Oct 14, 2026
- IRS, Instructions for Form 8911, checked Oct 14, 2026
- U.S. Access Board, EV charging guidance, checked Oct 14, 2026
- NFPA 70, National Electrical Code (Article 625), checked Oct 14, 2026
- Rocky Mountain Power, business EV charging, checked Oct 14, 2026
- Salt Lake City Building Services, checked Oct 14, 2026
- DOE Alternative Fuels Data Center, Utah laws and incentives, checked Oct 14, 2026
- Waymo, Where we're going, checked Oct 14, 2026
- BEA Regional Price Parities, 2024, checked Oct 14, 2026
- NOAA NCEI, U.S. Climate Normals 1991-2020, checked Oct 14, 2026
Last updated

About the author
John Davis
Content Writer
John Davis is the Content Writer at Wins Parking. He writes the Wins Parking blog and the site's parking guides, cost guides and planning resources on parking design, construction, management and EV charging. John also works on Wins Parking's senior leadership projects.
Ready to Unlock Your Parking Revenue?
Get a free, no-obligation proposal. Tell us about your property and we'll show you what's possible.
Or call us directly at (970) 279-1744